Chronology

1988

The company has continuously developed and permanently adapted to rapidly changing market requirements since its founding as an individual enterprise with a single lorry in 1988 in Pötsching, Burgenland.



1990/91

A new, efficient and future-oriented operating facility in Unterfladnitz is added in 1996 due to continuous and rapid growth.



1997

In 1997, the individual enterprise is registered as a limited company with headquarters in Arndorf 72, 8181 St. Ruprecht. In the same year, an industrial property with a size of approximately 1.7 ha is purchased in Dietmannsdorf 29, 8181 St. Ruprecht.



1999

Begin of construction of an office building and storage hall with a size of 800 m2 on the industrial property.


 

2000

Company relocation to Königsdorf.


 

2001

Further licenses for Styria, region Weiz (postal code 8160) are acquired.


 

2005

Due to high customer demand and continuous company growth, 2,500 m2 of storage area are rented in St. Ruprecht.


 

2008

Construction of a production hall with a size of 1,300 m2 on the industrial property in Dietmannsdorf.
In further consequence, two additional storage halls with a size of approximately 2,920 m2 are rented in the immediate vicinity.



 

2010

Construction of a state-of-the-art logistics hall with a size of 2,700 m2 as well as new construction of the office building. In further consequence, all storage halls are equipped with cranes with a load capacity between 5 and 40 tons. In the same year, the former operating area of the company Extra with a size of approximately 4,000 m2 of storage and open storage area is taken over in Tannhausen, district Weiz.



2011

The property of the former company BackTec at 8181 St. Ruprecht is taken over in order to keep pace with constantly growing requirements of our customers. We have exclusively operated this site since the takeover. Heated production halls with a size of 3,800 m2 as well as office space with a size of 1,100 m2 are located here and made available for rent. An industrial area with a size of 1.8 ha is additionally available at this site; the construction of further storage halls is being planned.


 

2012

Acquisition of a storage hall with a size of 1,600 m2 in the industrial area Ilz in order to also optimally support our customers in the most southern areas. We currently employ a workforce of 90 persons and are constantly striving to provide our customers with optimal service and industry-relevant expertise at the highest level.



2013

The company has a fleet of 37 lorries and over 50 lorries for subcontractors. Hall areas have been expanded to 24,000 m2 and open storage areas to 30,000 m2.



2015

Construction of the new hall "MLZ" at 8200 Albersdorf, Frank-Stronach-Straße 11 in the record time of 3 months with a total area of 5,400 m2, which corresponds to a length of 130 m and a width of 40 m; the height is 10 m. The hall is divided into 3 areas separated by fire walls, 1 part block storage and 2 parts shelf storage. Warehouse management is performed directly on site in the integrated office.



2016

Construction of the "MLZ crane hall" at 8200 Albersdorf, Frank-Stronach-Straße 11 from February to April. The hall with a height of 16 m and a storage area of 3,750 m2 accommodates an impressive 32 t and 60 t crane and was expanded with an office wing on one side and a social tract on the other.